Question: Current Attempt in Progress Oriole Enterprises Ltd . has entered into a contract beginning in February 2 0 2 3 to build two warehouses for

Current Attempt in Progress
Oriole Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Blue Spruce Structures Ltd. The contract is a non-cancellable fixed-price contract for $10.2 million. The following data pertain to the construction period.
\table[[,2023,2024,2025],[Costs for the year,$3,915,000,4,785,000,1,200,000
CALCULATE THE AMOUNT OF GROSS PROFIT TO BE RECOGNIZED EACH YEAR OF THE CONTRACT