Custom Clubs produces handmade golf clubs. The process is labor intensive. The speed at which a club
Fantastic news! We've Found the answer you've been seeking!
Question:
Custom Clubs produces handmade golf clubs. The process is labor intensive. The speed at which a club can be built depends on the skill level of the individual worker. Management has established a standard of 2 labor hours per club. The standard wage rate is $12 per hour. During a recent month, 2,500 custom clubs were produced. Management was pleased that only 4,900 labor hours were worked; however, total wages amounted to $63,700.
Compute the total variance for labor, and determine how much is related to rate and efficiency components.
Labor variances: | ||||
Actual Labor Cost | ||||
Actual hours of labor | - | |||
Actual rate | $ - | |||
Actual cost of direct labor | $ - | |||
Standard Labor Cost | ||||
Output - number of clubs | - | |||
Standard hours per club | $ - | |||
Standard hours to achieve output | - | |||
Standard rate per hour | $ - | |||
Standard cost of direct labor | $ - | |||
Total labor variance (standard cost v. actual cost) | $ - | |||
Labor rate variance: | ||||
Standard rate | $ - | |||
Actual rate | - | |||
$ - | ||||
Actual hours | - | |||
Unfavorable labor rate variance | $ - | |||
Labor efficiency variance: | ||||
Standard hours | - | |||
Actual hours | - | |||
- | ||||
Standard rate | $ - | |||
Favorable labor efficiency variance | $ - | |||