Question: Cy wants to know if it would affect the projects end date if the above activity was started on day 18. What is your response
- Cy wants to know if it would affect the projects end date if the above activity was started on day 18. What is your response and justification?
| ES | EF | LS | LF |
| 17 | 24 | 19 | 26 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock