Question: Dave's earliest start (ES) and earliest finish (EF) are: Dave's latest start (LS) and latest finish (LF) are: Activity ABO C D E F
Dave's earliest start (ES) and earliest finish (EF) are: Dave's latest start (LS) and latest finish (LF) are: Activity ABO C D E F G I Q H Activity H ES 0 0 6 6 6 6 11 12 LS 14 EF 6 6 8 7 11 12 20 18 LF Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) ABCO D 6 621 1 44 A A EEGH 5696 B B C, E D, F
Step by Step Solution
There are 3 Steps involved in it
The images youve provided relate to project scheduling specifically using a method such as the Criti... View full answer