Question: d. AON diagram 8 7 D A 4 3 End B E Start 6 5 7 G F What is the expected project duration? O

d. AON diagram 8 7 D A 4 3 End B E Start 6 5 7 G
d. AON diagram 8 7 D A 4 3 End B E Start 6 5 7 G
d. AON diagram 8 7 D A 4 3 End B E Start 6 5 7 G F What is the expected project duration? O 15 O 18 O 20 40