Question: D C A B tion A project team just completed a major milestone and is now on track to deliver the project ahead of the

A meeting is being scheduled for the scrum master, product owner and project team to discuss what went well and what did not go well during last project iteration and to plan improvements for future iterations. Which meeting objectives are being described? Iteration planning meeting Retrospective meeting Daily stand-up meeting Backlog refinement meeting