Question: D D 15 20 D 1 E B 2 8 Consider the following website development project: Normal Duration Crash Duration Normal Cost Activity Predecessors Crash

D D 15 20 D 1 E B 2 8 Consider the following

D D 15 20 D 1 E B 2 8 Consider the following website development project: Normal Duration Crash Duration Normal Cost Activity Predecessors Crash Cost (Weeks) (Weeks) ($,000) ($,000) NONE 2 1 10 15 NONE 8 5 21 4 3 24 B 1 7 7 1 15 F C,D 5 3 10 16 G E 6 2 36 Answer the following questions: a) (1 pt) Draw the network. b) (1 pt) What is the critical path and time? C) (1 pts)What is the normal cost? d) (1 pt) Calculate the Activity Slope for each activity. e) (5 pts) Which activities should be expedited to decrease the delivery time by seven weeks. f) (1 pt) What is this cost? N 12

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!