Question: D evelop a complete MRP plan. The gross requirements for finished tables are 40 units in week 7 and 100 units in week 8, respectively.

Develop a complete MRP plan. The gross requirements for finished tables are 40 units in week 7 and 100 units in week 8, respectively. (15pts; 3pts per "Table.") Please make sure you copy those 5 tables to your response.

Develop a complete MRP plan. The gross requirements for finished tables are

Table 1 2 3 4 5 6 7 8
Gross requirement
On-hand/scheduled receipts
Net requirement
Planned order releases

Leg Assembly 1 2 3 4 5 6 7 8
Gross requirement
On-hand/scheduled receipts
Net requirement
Planned order releases

Top 1 2 3 4 5 6 7 8
Gross requirement
On-hand/scheduled receipts
Net requirement
Planned order releases

Rails 1 2 3 4 5 6 7 8
Gross requirement
On-hand/scheduled receipts
Net requirement
Planned order releases

Leg 1 2 3 4 5 6 7 8
Gross requirement
On-hand/scheduled receipts
Net requirement
Planned order releases

Part 2:

(continued from the above MRP deployment) What type of inventory management system MRP is ?

Multiple choice:

A. P system

B. independent demand inventory management system

C. Q system

D. dependent demand inventory management system

Table Leg Assemblv(1) Top(1) \begin{tabular}{lll} Item & Quantity on Hand & Lead Time \\ \hline Table & 20 & 1 week \\ Leg Assembly & 0 & 3 weeks \\ Top & 10 & 1 week \\ Rails & 20 & 1 week \\ Legs & 20 & 2 weeks \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!