Question: B=2A C=3A D = 1B +2C E = 3B F = 3C Gross Material Requir Schedule Lead times for item A and its components are

B=2A C=3A D = 1B +2C E = 3B F = 3C Gross Material

B=2A C=3A D = 1B +2C E = 3B F = 3C Gross Material

B=2A C=3A D = 1B +2C E = 3B F = 3C Gross Material

B=2A C=3A D = 1B +2C E = 3B F = 3C

Gross Material Requir Schedule Lead times for item A and its components are given in the table below: Item B D E F Lead 1 week 2 weeks 3 weeks 2 weeks 1 week 2 weeks time Using the lead time information given above, develop the gross material requirements plan with a production schedule that will satisfy the demand of 100 units of item A by week 8 (as shown in the table below). Please note that you are asked to develop the gross material requirements plan with Required date and Order release date for items A, B, C, and D only. In the table below, A, B, C, and D represent items A, B, C, and D, respectively. Week 1 2 3 4 5 6 7 8 A. Required date 100 Order release date B. Required date Order release date C. Required date Week 1 4 6 7 2 3 5 8 100 A. Required date Order release date B. Required date Order release date C. Required date Order release date D. Required date Order release date Interpretation of the table: . In the table above, 100 is given at the intersection of "A. Required date and "Week 8". It means that 100 units of item A are required in Week 8. The next question is then: how many units of item A must be ordered and when in which week) those units of item A must be ordered (if ordered from a supplier) or when the production of item A must be started. This question corresponds to Order release date in the table. . For item B, C, and D, you will be asked the similar questions: 1) How many units are required and when (in which week) those units are required (this corresponds to Required date in the table); and 2) How many units must be ordered and when (in which week) those units must be ordered (this corresponds to Order release date in the table). Question 37 (2 points) units must be ordered in For item A: Week . Round the final answer (if it is not a whole number) to the nearest whole number. Question 38 (2 points) units are required in For item B: Round the final answer (if it is Week not a whole number) to the nearest whole number. Question 39 (2 points) A units must be ordered in For item B: Round the final answer (if it is Week not a whole number) to the nearest whole number. Question 40 (2 points) For item C: A units are required in Round the final answer (if it is A/ Week

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!