Question: d. For reducing project duration, resources from (non-critical path or critical path) activities should be borrowed to speed activities on the (non-critical path or critical



d. For reducing project duration, resources from (non-critical path or critical path)activities should be borrowed to speed activities on the (non-critical path or critical path)
Normal Immediate Time (days) Predecessor(s) 0.0 7.0 A 0.2 B 1.5 B 1.0 B 2.0 D Job Letter Description A Start B Design Order special accessories D Build frame E Build doors F Attach axles, wheels, gas tank G Build body shell H Build transmission and drivetrain 1 Fit doors to body shell J Build engine K Bench-test engine L Assemble chassis M Road-test chassis N Paint body 2.0 B 1.0 B 1.5 GE B 5.0 3.0 J 1.5 F, H, K L 1.0 3.0 1 1.0 1.5 ZZU 5.0 Q R Install wiring Install interior Accept delivery of special accessories Mount body and accessories on chassis Road test car Attach exterior trim Finish 2.0 M, O, P, Q R 1.5 T 1.0 S U 0.0 T The Rover 6 is a new custom-designed sports car. An analysis of the task of building the Rover 6 reveals the following list. Click the icon to view the list of relevant activities, their immediate predecessors, and their durations. This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-J-K-L-M-R-S-T-U. The total project completion time for custom designed Rover 6 car is 22 days. (Round your response to one decimal place.) c) For Rover 6 to be completed 2 days earlier, one should buy preassembled transmissions and drivetrains speed delivery of special accessories by 3 days speed the building of body shell none of the aboveStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts