Question: d . If the project appears to be more or less risky than an average project, find its risk - adjusted NPV , IRR, and

d. If the project appears to be more or less risky than an average project, find its risk-adjusted NPV, IRR, and payback. CV range of firm's average-risk project: 0.8 to 1.2 Low-risk WACC =8% WACC =10% High-risk WACC =13% Risk-adjusted WACC = Risk adjusted NPV =($47,839) IRR =7.70% Payback =3.50 e. On the basis of information in the problem, would you recommend that the project be accepted?