Question: D Question 6 3 pts A project manager is conducting the initial process of identifying stakeholders for a new project. The project manager has just

D Question 6 3 pts A project manager is conducting the initial process of identifying stakeholders for a new project. The project manager has just compiled a list of potential stakeholders' names. What should the project manager do next? O Invite the identified stakeholders to the project kick-off meeting O Complete the communication plan Develop the stakeholder engagement plan O Conduct stakeholder analysis Previous Next . Not saved Submit Quiz