Question: A project manager is conducting the initial process of identifying stakeholders for a new infrastructure development project. The project manager has just compiled a list

A project manager is conducting the initial process of identifying stakeholders for a new infrastructure development project. The project manager has just compiled a list of potential stakeholders’ names. What should the project manager do next?

A. Invite the identified stakeholders to the project kick-off meeting B. * Conduct stakeholder analysis C. Complete the Project Stakeholder Management process D. Develop the stakeholder engagement plan