Question: d . the stakeholders.To control the project, the project team should collect a . the names and descriptions of the resources used on the project.

d. the stakeholders.To control the project, the project team should collect
a. the names and descriptions of the resources used on the project.
b. anecdotal information from the project team members.
c. data on the actual performance and information about any changes to the project scope, schedule, and budget.
d. reports on the amount of money spent because that is the amount of work completed.