Question: Daily demand for product sample kits is normally distributed with a mean of 35 units and a standard deviation of 4. Supply is virtually certain
Daily demand for product sample kits is normally distributed with a mean of 35 units and a standard deviation of 4. Supply is virtually certain with a lead time of 9 days. The cost of placing an order is $20, and annual carrying costs for one kit is 25 percent. The price of one kit is $12.50. If a 99% service level is desired, what is the safety stock?
Group of answer choices
28
343
4
325