Question: Daniel has been assigned as a project manager in the middle of a project. He is currently in the process of taking handover from the
Daniel has been assigned as a project manager in the middle of a project. He is currently in the process of taking handover from the previous project manager. He gets to know that the client is not happy with the performance of the project even if it is performing within the baselines. What should Daniel do as the immediate next step?
Select one:
a. Call a meeting with the customer
b. Refer to communications plan
c. Call a meeting with the project team
d. Check risk management plan