Question: Data for a project are given in the table below. Efficiency, Preliminary Efficiency, Normal Time to Completion, Minimum Time to Completion, Cost for Normal Time

Data for a project are given in the table below.

Efficiency, Preliminary Efficiency, Normal Time to Completion, Minimum Time to Completion, Cost for Normal Time (CU million), cost for minimum time (million) Data for a project are given in the table below.

The network diagram of this project was drawn and the early/late times of the nodes were found with the CPM method. The resulting situation is as follows:

Data for a project are given in the table below.

For the project in question, do the following:

a) Calculate the total abundances for each activity. b) Identify the critical path. c) What is the cost of completing the project in 7 days?

\begin{tabular}{|c|c|c|c|c|c|} \hline A & & 2 & 2 & 210 & 210 \\ \hline B & & 6 & 4 & 400 & 600 \\ \hline C & & 4 & 3 & 500 & 750 \\ \hline D & A & 3 & 2 & 540 & 600 \\ \hline E & C & 5 & 3 & 750 & 950 \\ \hline F & A & 4 & 3 & 275 & 310 \\ \hline G & BDE & 2 & 1 & 100 & 125 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!