Question: Data for a small project are tabulated as: Activity Preceding Activities Duration (in Days) Reusable Resource Required A None 4 2 B None 3 1

Data for a small project are tabulated as:

Activity

Preceding Activities

Duration (in Days)

Reusable Resource Required

A

None

4

2

B

None

3

1

C

B

2

0

D

A

6

4

E

A

10

2

F

D, C

8

1

G

B

16

3

H

E

2

1

Maximum Reusable Resource Available:

4

  1. Determine the critical path of the network without consideration for resource constraint(s).
  2. Determine the ranks of activities based on Resource Over Time (ROT) algorithm.
  3. Utilizing the ROT ranking, re-schedule the project to determine:
    1. The minimum length of the project allowing the maximum available resources.
    2. Number of iterations needed to reach the answer in part-i.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!