Question: QUESTION 7 Consider a project and a required resource with the following information: Activity Preceding Activities Duration, days Resource Hours Needed per day A -
QUESTION 7
-
Consider a project and a required resource with the following information:
Activity
Preceding Activities
Duration, days
Resource Hours Needed per day
A
-
4
3
B
-
5
3
C
-
2
4
D
B, C
3
6
E
A, B
5
1
F
D
4
2
Time-phased resource-loading table for this project, based on earliest start, is:
Activity - day
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
A
3
3
3
3
B
3
3
3
3
3
C
4
4
D
6
6
6
E
1
1
1
1
1
F
2
2
2
2
If the maximum acceptable allocation per day for this recourse is 8 hours, prepare the resource-leveling table for this resource. Hence, the project will complete, on the earliest date, by the end of Day: