Question: QUESTION 7 Consider a project and a required resource with the following information: Activity Preceding Activities Duration, days Resource Hours Needed per day A -

QUESTION 7

  1. Consider a project and a required resource with the following information:

    Activity

    Preceding Activities

    Duration, days

    Resource Hours Needed per day

    A

    -

    4

    3

    B

    -

    5

    3

    C

    -

    2

    4

    D

    B, C

    3

    6

    E

    A, B

    5

    1

    F

    D

    4

    2

    Time-phased resource-loading table for this project, based on earliest start, is:

    Activity - day

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    A

    3

    3

    3

    3

    B

    3

    3

    3

    3

    3

    C

    4

    4

    D

    6

    6

    6

    E

    1

    1

    1

    1

    1

    F

    2

    2

    2

    2

    If the maximum acceptable allocation per day for this recourse is 8 hours, prepare the resource-leveling table for this resource. Hence, the project will complete, on the earliest date, by the end of Day:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!