Question: Data for Office Automation, Inc. Activity Description Immediate Predecessors Normal Time Crash Time Normal Cost ( $ ) Crash Cost ( $ ) A Plan
Data for Office Automation, Inc.
Activity Description Immediate Predecessors Normal Time Crash Time Normal Cost $ Crash Cost $
A Plan needs
B Order equipment A
C Install equipment B
D Set up training lab A
E Training course D
F Testing system C E
Use the Trial and Error Method to solve this problem and crash off two weeks from the project. What is the Total Cost of Crashing including the Normal Cost?