Question: Data for Office Automation, Inc. Activity Description Immediate Predecessors Normal Time Crash Time Normal Cost ( $ ) Crash Cost ( $ ) A Plan
Data for Office Automation, Inc.
Activity Description Immediate Predecessors Normal Time Crash Time Normal Cost $ Crash Cost $
A Plan needs
B Order equipment A
C Install equipment B
D Set up training lab A
E Training course D
F Testing system C E
a Show the network for the project.
b Develop an activity schedule for the project using normal times.
c What are the critical path activities and what is the expected project completion time?
Use the Trial and Error Method to solve this problem and crash off two weeks from the project. What is the Total Cost of Crashing including the Normal Cost?