Question: Data for the website development project is as follows: Immediate Activity Predecessor Time (days) Start A Start 40 B Start 30 A 10 D A

Data for the website development project is as

Data for the website development project is as follows: Immediate Activity Predecessor Time (days) Start A Start 40 B Start 30 A 10 D A 50 E B 40 F B 10 G DE 30 - H F 50 1 20 J GH 10 End 1,J The critical path is The duration is ES at node G is LF at node B is EF at node J is