Question: Data on small project is given as below. Draw the AON of the project then determine the critical path time and activities? table [

Data on small project is given as below. Draw the AON of the project then determine the critical path time and activities?
\table[[Activity,predecssor,Duration/week],[A,-,9],[B,-,6],[C,-,4],[D,A,10],[E,A,16],[F,B,9],[G,B,5],[H,C,8],[I,D,E,4],[J,F,G,6],[K,I,7]]