Question: DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day Consider table below as demonstration of a resource-limited project. Assume that

DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day

Consider table below as demonstration of a resource-limited project. Assume that you cannot schedule more than eight hours of work during any day of work. A None 5 4 B A 3 4 C A 4 4 D A 6 3 E C 5 3 F C 6 2 G D 4 4

DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day A None 5 4 B A 3 4 C A 4 4 D A 6 3 E C 5 3 F C 6 2 G D 4 4

Identify if there are any days that involves resource conflict and give their status

How would you reconfigure the resource loading to resolve this conflict

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!