Question: DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day Consider table below as demonstration of a resource-limited project. Assume that
DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day
Consider table below as demonstration of a resource-limited project. Assume that you cannot schedule more than eight hours of work during any day of work. A None 5 4 B A 3 4 C A 4 4 D A 6 3 E C 5 3 F C 6 2 G D 4 4
DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day A None 5 4 B A 3 4 C A 4 4 D A 6 3 E C 5 3 F C 6 2 G D 4 4
Identify if there are any days that involves resource conflict and give their status
How would you reconfigure the resource loading to resolve this conflict