Question: date requested by the owner. The Mueller project manager prepared the following project network. i ) Estimates of the optimistic, most probable, and pessimistic times
date requested by the owner. The Mueller project manager prepared the following project network.
i
Estimates of the optimistic, most probable, and pessimistic times in weeks for the activities are as follows.
begintabularcccc
hline Activity & Optimistic & Most Probable & Pessimistic
hline A & & &
hline B & & &
hline C & & &
hline D & & &
hline E & & &
hline F & & &
hline
endtabular
a Find the critical path. Enter your answers as a commaseparated list.
b What is the expected project completion time in weeks
weeks
c Based only on the critical path, what is the estimated probability the project can be completed in weeks as requested by the owner? Round your answer to four decimal places.
d Based only on the critical path, what is the estimated probability the building project could run more than months late? Use weeks for this calculation. Round your answer to four decimal places.
e What should the construction company tell the owner? Enter your freeform answer using as many characters as necessary.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock