Question: You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new
You may need to use the appropriate technology to answer this question.
Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the week completion date requested by the owner. The Mueller project manager prepared the following project network.
A project network with activities and directed arcs is shown.
Activity Start is connected to activity A
Activity A is connected to activity B to activity C and to activity D
Activity B is connected to activity F
Activity C is connected to activity E and to activity F
Activity D is connected to activity E
Activity E is connected to activity G and to activity Finish.
Activity F is connected to activity G and to activity H
Activity G is connected to activity H
Activity H is connected to activity Finish.
Activity Finish has no arcs directed to other activities.
Estimates of the optimistic, most probable, and pessimistic times in weeks for the activities are as follows.
Activity Optimistic Most Probable Pessimistic
A
B
C
D
E
F
G
H
a
Find the critical path. Enter your answers as a commaseparated list.
Correct: Your answer is correct.
b
What is the expected project completion time in weeks
Correct: Your answer is correct.
weeks
c
Based only on the critical path, what is the estimated probability the project can be completed in weeks as requested by the owner? Round your answer to four decimal places.
Incorrect: Your answer is incorrect.
d
Based only on the critical path, what is the estimated probability the building project could run more than months late? Use weeks for this calculation. Round your answer to four decimal places.
Incorrect: Your answer is incorrect.
e
What should the construction company tell the owner? Enter your freeform answer using as many characters as necessary.i
Estimates of the optimistic, most probable, and pessimistic times in weeks for the activities are as follows.
tableActivityOptimistic,Most Probable,PessimisticABCDEFGH
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock