Question: Day 1 2 3 4 5 $ 4 0 0 $ 4 0 0 $ 4 0 0 $ 4 0 0 $ 4 0
Day
$ $ $ $ $What is the Budget At Completion BAC
What is the Actual Cost AC
What is the Earned Value EV
What is the Planned Value PV
What is the Cost Variance CV
What is the Schedule Variance SV
What is the Cost Performance Index CPI
What is the Schedule Performance Index SPI
Are we above budget or under budget?
Are we ahead of time or behind time?