Question: Define project scope and objectives for your project on 3-axis Router / Measuring Machine. These tasks should be specific and clear. Consider this project. What
Define project scope and objectives for your project on 3-axis Router / Measuring Machine. These tasks should be specific and clear. Consider this project. What happens if Task C duration increases by 2 days? Task Duration (days) Predecessor A 5 none B 4 A C 3 A D 7 B E 10 C,D