Question: Defined as the difference between earned value (EV) and planned value (PV), ______ is used to indicate if work is ahead of or behind the

Defined as the difference between earned value (EV) and planned value (PV), ______ is used to indicate if work is ahead of or behind the planned schedule. A. planned value (PV) B. earned value (EV) C. schedule variance (SV) D. cost variance (CV)