Question: Project 1 Budget at completion ( BAC ) = $ 5 0 , 0 0 0 Actual Cost ( AC ) = $ 4 0

Project 1
Budget at completion (BAC)= $50,000
Actual Cost (AC)= $40,000
Earned Value (EV)= $35,000
Planned Value (PV)= $37,000
Project 2
Budget at completion (BAC)= $20,000
Actual Cost (AC)= $15,000
Earned Value (EV)= $18,000
Planned Value (PV)= $16,000
Directions
Complete the earned value calculations for each problem to determine:
Cost variance (CV)
Schedule variance (SV)
Cost performance index (CPI)
Schedule performance index (SPI)
Estimate at completion (EAC)
Compose a statement on each projects status.
Is the project ahead or behind schedule?
Is the project over or below budget?
Is the earned value performance better or worse than planned?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!