Question: Project 1 Budget at completion ( BAC ) = $ 5 0 , 0 0 0 Actual Cost ( AC ) = $ 4 0
Project
Budget at completion BAC $
Actual Cost AC $
Earned Value EV $
Planned Value PV $
Project
Budget at completion BAC $
Actual Cost AC $
Earned Value EV $
Planned Value PV $
Directions
Complete the earned value calculations for each problem to determine:
Cost variance CV
Schedule variance SV
Cost performance index CPI
Schedule performance index SPI
Estimate at completion EAC
Compose a statement on each projects status.
Is the project ahead or behind schedule?
Is the project over or below budget?
Is the earned value performance better or worse than planned?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
