Question: Dell Computers' master budget shows that the planned activity level for next year is expected to be 50,000 machine hours. At this level of activity,
Dell Computers' master budget shows that the planned activity level for next year is expected to be 50,000 machine hours. At this level of activity, the following manufacturing overhead costs are expected: Indirect labor $720,000 Machine supplies 180,000 Indirect materials 210,000 Depreciation on factory building 150,000 Total manufacturing overhead $1.260,000 A flexible budget for a level of activity of 60,000 machine hours would show total manufacturing overhead costs of $1,362,000. $1,482,000 $1,260,000. O $1,512,000