Question: Delta engineering is using MRP for their production. Consider the following MRP lot - sizing problem, the net requirements are shown for eight scheduling weeks

Delta engineering is using MRP for their production. Consider the following MRP lot-sizing problem, the net requirements are shown for eight scheduling weeks
Weekly net requirements
\table[[Week,1,2,3,4,5,6,7,8],[Requirement,50,60,70,60,95,75,60,55]]
The other information are as follows
\table[[Cost per item,10$
 Delta engineering is using MRP for their production. Consider the following