Question: demand = 330 units. operational for 7.5 hours a) What is the workstation cycle time? b) What is the theoretical minimum number of workstations? c)

demand = 330 units.
operational for 7.5 hours
a) What is the workstation cycle time?
b) What is the theoretical minimum number of workstations?
c) Rule: Assigning tasks based on longest operating time:
d) What is the efficiency
PERFORMANCE TIME (SECONDS) PRECEDING TASKS TASK PERFORMANCE TIME (SECONDS) PRECEDING TASKS TASK FL-IO owLUI J, KStep by Step Solution