Question: Demand for a power steering gear assembly is given by Currently there are 4 0 parts on hand. The lot - sizing rule is fixed
Demand for a power steering gear assembly is given by
Currently there are parts on hand. The lotsizing rule is fixed order period using two periods. Lead time
is four periods.
a Determine the planned order release schedule for the gear
b Suppose each gear assembly requires two pinions. Currently there are pinions on
hand, the lotsizing rule is lotforlot, and the lead time is one period. Determine the gross
requirements and then the planned order release schedule for pinions.