Question: Demand is 4 , 8 0 0 units The Action Toy Company has decided to manufacture a new train set, the production of which is
Demand is units The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is units perhour workweek:Task Performance Time seconds Immediate Predecessors
A
B A
C A
D A
E B C
F D EThis exercise only contains parts b c d e and f
Part
b Given the demand, the cycle time for the production of the new train set
enter your response here seconds round your response to one decimal place