Question: Demand is 4 , 8 0 0 units The Action Toy Company has decided to manufacture a new train set, the production of which is

Demand is 4,800 units The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is units per40-hour workweek:Task Performance Time (seconds) Immediate Predecessors
A 20-
B 27 A
C 14 A
D 15 A
E 10 B, C
F 27 D, EThis exercise only contains parts b, c, d, e, and f.
Part 2
b) Given the demand, the cycle time for the production of the new train set=
enter your response here seconds (round your response to one decimal place).