Question: Depending on the below table, please answer the below questions: Prepare a network plan for the project using AON or AOA Calculate the Slack time

Depending on the below table, please answer the below questions:

Prepare a network plan for the project using AON or AOA

Calculate the Slack time for each activity.

Determine the Critical Path.

Calculate the Expected time for each activity.

Calculate the variance for each activity.

Calculate the project variance.

Calculate the crash cost per time for each activity.

We need to reduce the project duration by one day, which activity will be the one that we will reduce its duration by one day and why?

Activity

Duration (Days)

Immediate Predecessors

Normal Cost

Crash Time

Crash Cost

Optimistic time

Pessimistic

A

2

-

400

1

500

1

3

B

10

A

3000

8

3600

8

13

C

7

A

2800

5

3400

5

9

D

15

B

6000

12

7200

12

20

E

5

B

3000

-

-

-

-

F

6

C

3000

5

3500

5

8

G

3

E, F

2400

-

-

H

6

F

4200

3

5400

3

10

I

3

D, G, H

600

-

-

-

-

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!