Question: 2. Below is the table which includes the information of a new project of ABC Inc. The deterministic time for each activity (from activity A


2. Below is the table which includes the information of a new project of ABC Inc. The deterministic time for each activity (from activity A to activity G ) is in the table. Please answer the following questions: 1) Draw the network of the project corresponding to the information of Table 1. 2) Which path is the critical path? What is the length of the expected time of the project? 3) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. Please complete the table below
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
