Question: Description For this assignment, provide a periodic Earned Value Status and a one-page Executive Status report required by the PMO. You may make realistic assumptions

Description

For this assignment, provide a periodic Earned Value Status and a one-page Executive Status report required by the PMO. You may make realistic assumptions regarding project details. You are in charge of the Innovation project. Given the following project network, baseline, and status information,develop status reports for periods 1-8 and complete the performance indexes table.Calculate the forecasted EAC and the forecasted VAC. Based on your data, what is the current status of the project (use the status information from period 8)? At completion?

ID Budget ($000) 1 23456 7 8 9 10 11 12 >>A 100 50 50 B 250 100 50 100 C 450 150

ID Budget ($000) 1 23456 7 8 9 10 11 12 >> A 100 50 50 B 250 100 50 100 C 450 150 150 150 D 200 100 100 LU E 300 200 100 LL F 300 100 50 150 G 200 150 50 H 200 13 100 100 Total 2000 50 50 250 200 250 100 100 300 150 300 50 100 100 Cumulative 50 100 350 | 550 800 900 1000 1300 1450|1750|1800 1900 2000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!