Part 1. Draw a correct logic diagram for the activities and relationships listed below (10 points):
\table[[Activity ID,Activity Description,Dur.,Predecessor],[A,Activity A,2,None],[B,Activity B,3,A],[C,Activity C,4,A],[D,Activity D,2,C],[E,Activity E,3,B],[F,Activity F,4,D],[G,Activity G,3,E],[H,Activity H,2,E],[I,Activity I,3,G, H, F]]
Part 2. Once you complete the diagram, create a precedence Network diagram for the activities, relationships and durations shown in the chart above. Using the logic diagram created in Part 1, use the Forward Pass to calculate the Early Start (ES) and Early Finish (EF) dates and use the Backward Pass to calculate the Late Start (LS) and Late Finish (LF) dates for each activity. Finally, using either the start dates or the finish dates calculate the Total float (TF) for each activity and highlight the critical path with a Bold red line. (15 points)
Description Switch To Dark Mode You will submit

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!