Question: Description This assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for

Description
This assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for the project below.
Instructions
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 21 days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than the agreed 21 days.
Draw a project network given the information below. Then, do the following:
Complete the forward and backward pass
Determine the critical path
Compute the Total slack for all activities
Determine which activities have free float
\table[[ID,Activity,Predecessor,Duration],[A,Prepare Site,None,2],[B,Pour Foundation,A,3],[C,Erect Frame,B,4],[D,Roof,C,4],[E,Windows,C,1],[F,Doors,C,1],[G,Electrical,C,3],[H,Rough-In Frame,D,E,F,2],[I,Door Opener,F, G,1],[J,Paint,H, I,2],[K,Clean Up,J,1]]
 Description This assignment is meant for you to practice the critical

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!