Question: Design-->Write Manual -->System Test Luestion 15 Code Entry Unit Test 30 Days 16 Days Design System Test Unit Test Code Update 16 Days 15 Days

Design-->Write Manual -->System Test Luestion 15
Design-->Write Manual -->System Test Luestion 15 Code Entry Unit Test 30 Days 16 Days Design System Test Unit Test Code Update 16 Days 15 Days 15 Days 16 Days Code Query Unit Test 7 Days 16 Days Write Manual 30 Days What it the longest time we can delay the code update without delaying the entire project? 7 days 16 days 30 days 14 days