Question: detailed answer PLEASE these are the only information given 1/ calculate the total cost 2/ redraw the network diagram wothe the early start early finish
detailed answer PLEASE
these are the only information given
Activity Normal crash namal Cot Gash Cost 3 3 4 3 SO 3 4 4 5 Loo Ac 38 Acu start frush Aca ACS 1. Calculate total cost 2. fell the table, redraw the table network dagan. 2 Project duration Cuted ball Geded onlusly the proglect Activity Normal crash namal Cot Gash Cost 3 3 4 3 SO 3 4 4 5 Loo Ac 38 Acu start frush Aca ACS 1. Calculate total cost 2. fell the table, redraw the table network dagan. 2 Project duration Cuted ball Geded onlusly the proglect
1/ calculate the total cost
2/ redraw the network diagram wothe the early start early finish and fill the table
1st column : project duration
2nd column : critical path
3rd column : crashed activity
4th column : total project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock