Question: Determine a detailed budget from the given information below: Software & Database Development cost : $12,000 - $20,000 (this includes the software development, testing, and

Determine a detailed budget from the given information below:

Software & Database Development cost: $12,000 - $20,000 (this includes the software development, testing, and deployment costs)

Hardware and infrastructure costs: $7,000 - $9,000 (this includes the cost of servers, data storage, and other network components)

Training costs: $2,000 - $4,000 (mainly the training for customer service agents and some data analysts)

Maintenance and support costs: $3,000 - $5,000 (based on annual upkeep costs)

Project & other costs: $10,000 - $12,000 (Mainly project management, consulting, and some minor legal fees)

Total project budget: $34,000 - $50,000 5

Reduction in adjustment payouts: Based on the prediction of a reduced number of false claims, duplicate claims, and claims made in error, Rogers Telecommunications can expect to save $1,000 - $2,500 per month, or $12,000 - $30,000 per year.

Reduction in adjustments administration costs: Based on the prediction of increased productivity, scale, and other economic benefits, the cost of administering the program can be cut in half to $1,250 per month, or $15,000 per year.

See Exhibit A for the Net Present Value (NPV) & Return on Investment (ROI) The NPV of $21,166 in the first scenario and $130,606 in the second scenario are both positive, which indicates that the Adjustment Lobby is expected to generate more cash flows than the investment costs. The ROI is also both positive and quite high meaning the project will be a worthwhile investment.

Exhibit A: Net Present Value & Return on Investment

Risk-Free Rate 3.5%
Minimum NPV/ROI Maximum NPV/ROI
Software & Database Development Costs -$20,000 -$12,000
Hardware & Infrastructure Costs -$9,000 $7,000
Training Costs -$4,000 -$2,000
Maintenance & Support Costs -$5,000 -$3,000
Project & Other Costs -$12,000 -$10,000
Total Project Budget -$50,000 -$34,000
Reduction in Adjustment Payout $12,000 $30,000
Reduction in Adjustment Administration Costs $15,000 $15,000
NPV $21,166 $130,606
ROI 21.71% 192.07%

Things the budget must include are:

  1. Budget Planning
  2. Budget Cost Summary
  3. Baseline Cost Report- histogram
  4. Cost breakdown
  5. Task/ Account Group/ Work Package/ Cost
  6. Cumulative Cost
  7. S-curve- Earliest start
  8. S-curve- Latest start
  9. Budget Breakdown- Time phase budget
  10. Contingency reserve
  11. Management reserve

Task Start date End Date Duration (days) Dependencies
1 Jan 9, 2023 Jan 11, 2023 2 Start
2 Jan 9, 2023 Feb 3, 2023 25 1SS
3 Feb 4, 2023 Feb 21, 2023 17 2FS
4 Feb 22, 2023 Mar 14, 2023 20 3FS
5 Mar 15, 2023 Mar 20, 2023 5 3FS
6 Mar 21, 2023 Apr 1, 2023 11 5FS
7 Jan 9, 2023 Feb 23, 2023 45 2SS
8 Feb 24, 2023 Mar 16, 2023 20 7FS
9 Mar17, 2023 Mar 22, 2023 5 8FS
10 Mar 23, 2023 Apr 1, 2023 9 9FS
11 Mar 17, 2023 Mar 31, 2023 14 9SS
12 Apr 1, 2023 Apr 8, 2023 7 10FS
13 Apr 9, 2023 Apr 30, 2023 21 12FS
14 Apr 30, 2023 Jun 9, 2023 40 13FS
15 Jun 10, 2023 Jun 24, 2023 14 14FS
16 Jun 25, 2023 Jul 10, 2023 15 15FS
17 Jul 11, 2023 Jul 21, 2023 10 16FS
18 Jul 22, 2023 Aug 11, 2023 20 17FS
19 Aug 12, 2023 Oct 9, 2023 60 18FS
20 Oct 10, 2023 Oct 20, 2023 10 19FS
21 Oct 21, 2023 Oct 23, 2023 2 20FS
22 Oct 10, 2023 Nov 1, 2023 22 20SS
23 Nov 1, 2023 Nov 22, 2023 21 22FS
24 Nov 23, 2023 Nov 24, 2023 1 23FS
25 Nov 25, 2023 Dec 22, 2023 27 24FS
26 Nov 25, 2023 Dec 27, 2023 32 25SS
27 Dec 28, 2023 Dec 27, 2023 1 25FS
28 Dec 28, 2023 Jan 4, 2024 7 27FS
29 Jan 5, 2024 Jan 9, 2024 4 28FS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!