Question: Determine options User Status Meetings PHASE 3 Finalize new program provisions Prepare user manual and training Conduct user training IMPLEMENTATION Critical Non - Critical Progress
Determine options
User Status Meetings
PHASE
Finalize new program provisions
Prepare user manual and training
Conduct user training
IMPLEMENTATION
Critical
NonCritical
Progress to Date
Assume that today is April st According to the bar chart schedule for the MDI Project presented above, which of the following tasks is furthest behind schedule?
a Task #
b Task #
c Task #
d Task #