Question: Determine Predecessor, Optimistic time, pessimistic time, expected time, and most likely time for each of the following tasks required to determine the Critical Path (**Calculate
Determine Predecessor, Optimistic time, pessimistic time, expected time, and most likely time for each of the following tasks required to determine the Critical Path (**Calculate for all of the tasks given below in the table**)
Non-critical and critical activities should be determined through AON
| Task | Start date | End Date | Duration (days) | Dependencies |
| 1 | Jan 9, 2023 | Jan 11, 2023 | 2 | Start |
| 2 | Jan 9, 2023 | Feb 3, 2023 | 25 | 1SS |
| 3 | Feb 4, 2023 | Feb 21, 2023 | 17 | 2FS |
| 4 | Feb 22, 2023 | Mar 14, 2023 | 20 | 3FS |
| 5 | Mar 15, 2023 | Mar 20, 2023 | 5 | 3FS |
| 6 | Mar 21, 2023 | Apr 1, 2023 | 11 | 5FS |
| 7 | Jan 9, 2023 | Feb 23, 2023 | 45 | 2SS |
| 8 | Feb 24, 2023 | Mar 16, 2023 | 20 | 7FS |
| 9 | Mar17, 2023 | Mar 22, 2023 | 5 | 8FS |
| 10 | Mar 23, 2023 | Apr 1, 2023 | 9 | 9FS |
| 11 | Mar 17, 2023 | Mar 31, 2023 | 14 | 9SS |
| 12 | Apr 1, 2023 | Apr 8, 2023 | 7 | 10FS |
| 13 | Apr 9, 2023 | Apr 30, 2023 | 21 | 12FS |
| 14 | Apr 30, 2023 | Jun 9, 2023 | 40 | 13FS |
| 15 | Jun 10, 2023 | Jun 24, 2023 | 14 | 14FS |
| 16 | Jun 25, 2023 | Jul 10, 2023 | 15 | 15FS |
| 17 | Jul 11, 2023 | Jul 21, 2023 | 10 | 16FS |
| 18 | Jul 22, 2023 | Aug 11, 2023 | 20 | 17FS |
| 19 | Aug 12, 2023 | Oct 9, 2023 | 60 | 18FS |
| 20 | Oct 10, 2023 | Oct 20, 2023 | 10 | 19FS |
| 21 | Oct 21, 2023 | Oct 23, 2023 | 2 | 20FS |
| 22 | Oct 10, 2023 | Nov 1, 2023 | 22 | 20SS |
| 23 | Nov 1, 2023 | Nov 22, 2023 | 21 | 22FS |
| 24 | Nov 23, 2023 | Nov 24, 2023 | 1 | 23FS |
| 25 | Nov 25, 2023 | Dec 22, 2023 | 27 | 24FS |
| 26 | Nov 25, 2023 | Dec 27, 2023 | 32 | 25SS |
| 27 | Dec 28, 2023 | Dec 27, 2023 | 1 | 25FS |
| 28 | Dec 28, 2023 | Jan 4, 2024 | 7 | 27FS |
| 29 | Jan 5, 2024 | Jan 9, 2024 | 4 | 28FS |