Determine the earliest start time (EST), latest finish time (LFT), and total float for each task in
Fantastic news! We've Found the answer you've been seeking!
Question:
Determine the earliest start time (EST), latest finish time (LFT), and total float for each task in a tabular form and calculate Critical Path from those values.
Determine Predecessor, Optimistic time, pessimistic time, expected time, and most likely time for each of the following tasks required to determine the Critical Path
Task | Start date | End Date | Duration (days) | Dependencies |
1 | Jan 9, 2023 | Jan 11, 2023 | 2 | Start |
2 | Jan 9, 2023 | Feb 3, 2023 | 25 | 1SS |
3 | Feb 4, 2023 | Feb 21, 2023 | 17 | 2FS |
4 | Feb 22, 2023 | Mar 14, 2023 | 20 | 3FS |
5 | Mar 15, 2023 | Mar 20, 2023 | 5 | 3FS |
6 | Mar 21, 2023 | Apr 1, 2023 | 11 | 5FS |
7 | Jan 9, 2023 | Feb 23, 2023 | 45 | 2SS |
8 | Feb 24, 2023 | Mar 16, 2023 | 20 | 7FS |
9 | Mar17, 2023 | Mar 22, 2023 | 5 | 8FS |
10 | Mar 23, 2023 | Apr 1, 2023 | 9 | 9FS |
11 | Mar 17, 2023 | Mar 31, 2023 | 14 | 9SS |
12 | Apr 1, 2023 | Apr 8, 2023 | 7 | 10FS |
13 | Apr 9, 2023 | Apr 30, 2023 | 21 | 12FS |
14 | Apr 30, 2023 | Jun 9, 2023 | 40 | 13FS |
15 | Jun 10, 2023 | Jun 24, 2023 | 14 | 14FS |
16 | Jun 25, 2023 | Jul 10, 2023 | 15 | 15FS |
17 | Jul 11, 2023 | Jul 21, 2023 | 10 | 16FS |
18 | Jul 22, 2023 | Aug 11, 2023 | 20 | 17FS |
19 | Aug 12, 2023 | Oct 9, 2023 | 60 | 18FS |
20 | Oct 10, 2023 | Oct 20, 2023 | 10 | 19FS |
21 | Oct 21, 2023 | Oct 23, 2023 | 2 | 20FS |
22 | Oct 10, 2023 | Nov 1, 2023 | 22 | 20SS |
23 | Nov 1, 2023 | Nov 22, 2023 | 21 | 22FS |
24 | Nov 23, 2023 | Nov 24, 2023 | 1 | 23FS |
25 | Nov 25, 2023 | Dec 22, 2023 | 27 | 24FS |
26 | Nov 25, 2023 | Dec 27, 2023 | 32 | 25SS |
27 | Dec 28, 2023 | Dec 27, 2023 | 1 | 25FS |
28 | Dec 28, 2023 | Jan 4, 2024 | 7 | 27FS |
29 | Jan 5, 2024 | Jan 9, 2024 | 4 | 28FS |