Question: Determine The Capacity For A Multi-step Process Choose Choose Anything to drink? Cashier your side PANDA your entree 1 worker 1 worker 1 worker 1

Determine The Capacity For A Multi-step Process

Determine The Capacity For A Multi-step Process Choose Choose Anything to drink? Cashier your side PANDA your entree 1 worker 1 worker 1 worker 1 worker Info collected 0.5 min/order 1 min/order 0.5 min/order 0.8 min/order GOURMET Scenario 1: Assuming the demand rate at Panda Express is 10 orders/hour, 1) What is the flow rate? Is this process demand-constrained or capacity-constrained? 2) What is the utilization of the entre station