Question: DETERMINE THE COST, BASE WH, LOCAL SELF PREFORM WH, AND THE TOTAL LABOR COST. $75/hour self-perform rate 780 CY of mass excavation 0.2 hours/CY PF
DETERMINE THE COST, BASE WH, LOCAL SELF PREFORM WH, AND THE TOTAL LABOR COST.
$75/hour self-perform rate
780 CY of mass excavation 0.2 hours/CY PF of 1.5 210 CY of backfill and compaction 0.75 hours/CY PF of 0.8
340 CY Equipment Foundations 1.15 hours/CY PF of 1.5 Material Unit Cost - $15/CY Pump Truck Cost - $7000
Concrete Testing One lot per 200 CY of poured concrete Sub Cost of $200/lot
35 CY Epoxy Grouting 2.00 hours/CY PF of 0.9 Material Unit Cost - $25/CY
115 CY Catch Basins & Manholes Cast in Place 1.5 hours/CY PF of 1.25 Material Unit Cost - $15/CY
| Total Cost ($) |
|
| Base WH |
|
| Local Self Perform WH |
|
| Total Labor Cost ($) |
|
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock