Question: DETERMINE THE COST, BASE WH, LOCAL SELF PREFORM WH, AND THE TOTAL LABOR COST. $75/hour self-perform rate 780 CY of mass excavation 0.2 hours/CY PF

DETERMINE THE COST, BASE WH, LOCAL SELF PREFORM WH, AND THE TOTAL LABOR COST.

$75/hour self-perform rate

780 CY of mass excavation 0.2 hours/CY PF of 1.5 210 CY of backfill and compaction 0.75 hours/CY PF of 0.8

340 CY Equipment Foundations 1.15 hours/CY PF of 1.5 Material Unit Cost - $15/CY Pump Truck Cost - $7000

Concrete Testing One lot per 200 CY of poured concrete Sub Cost of $200/lot

35 CY Epoxy Grouting 2.00 hours/CY PF of 0.9 Material Unit Cost - $25/CY

115 CY Catch Basins & Manholes Cast in Place 1.5 hours/CY PF of 1.25 Material Unit Cost - $15/CY

Total Cost ($)

Base WH

Local Self Perform WH

Total Labor Cost ($)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!