Question: Determine the critical path for the project. What are the earliest and latest times for each node from 1 to 7 ? What is the

Determine the critical path for the project. What are the earliest and latest times for each node from 1 to 7? What is the total time for the project?
Compute the floats and identify the red-flagged activities for the project (noncritical activities with FF < TF), then develop the time schedule under the following conditions:
Activity (1,5) cannot start any earlier than 14.
Activities (5,6) and (5,7) use the same equipment, of which only one unit is available.
All other activities start as early as possible.